|
|
| |
|
|
| |
Bulletin |
|
| |
|
|
| |
COORDINATION MEETING THE BUILDINGS AND
HOUSING DEPARTMENT HELD ON 23.04.08
The Coordination meeting of the Buildings and
Housing Department was held on Wednesday,
23rd April at 11:30am,in the Conference Hall
of the Department.
The meeting was chaired by the P.C.E cum
Secretary of the department. The welcome
speech was addressed by the Additional
Secretary of the department. The P.C.E.cum
secretary welcomed all the officer and staff
present in the meeting. The list of all who
attend the meeting is appended at Annexure
A. He also welcomed the officers who have
recently joined the department on being
transferred to this department.
The meeting commenced as per the agenda
appended at Annexure B. |
|
| |
|
|
| |
1. REVIEW OF THE MINUTE OF THE LAST
MEETING HELD ON 22.05.07:
WEST DISTRICT
Science Collage at Soreng
The Sr. Accounts Officer was direct to
prepared the Utilization Certificate and
forward the same to Human Resource Developed
Department.
Construction of Sub-jail Complex at
Gyalshing
The Div.Engineer was instructed to submit
the revised estimate of the Sub-Jail Complex
at Gyalshing by the end of May.
Construction of I.R.B.HQ at Pipley (Phase
II)
The Superintending Engineer (Planning)
apprised the House that certain estimate for
the construction of I.R.B.HQ at Pipley needs
to be rectified.
The Div. Engineer (West) had been instructed
to pursue the matter with the P.H.E. and
Energy & Power Dept and the revised estimate
was to be submitted by 5th May.
Construction of Model Police Station at
Sombarey: |
|
| |
The work has come to
standstill after the court order to stop the
work on March’08’.The litigation is still
going on as has been proved to whom the land
under construction belongs to.
(I) The Superentending engineer
Planning,
Building & Housing Department
Gangtok
The P.C.E.cum Secretary apprised the House
that as per the law, the government should
pay the compensation for the land to the
owner. Since the asset is being constructed
in the behalf of the Police Deptt, the
Police Deptt. should be made to pat the
compensation.
The P.C.E.cum Secretary informed the House
that whenever such legal dispute aries, the
department officers/engineers, who are
expert in their field and know the case
better can always take the permission of the
chair and explain the case before the court.
The Div.Engineer (West) was therefore direct
to represent the case before the court and
convince them. The matter should be settled
amicably and the injection has to be lifted.
The Land Revenue’s 1978’s Notification may
also be considered if it favours the case.
Construction of the Research Centre for
Indian Nepalese Literature and Culture at
Kyongsa.
The field work has not yet started as the
fund needs to be transferred from the
Culture Affairs & Heritage Deptt. to the
Energy & Power Deptt. The Chief Engineer has
been advised to corresponding with the
Culture Affairs & Heritage Deptt. for the
transfer of funds to the Energy & Power
dept. copy of the same may also be sent to
the Chief Engineer (Energy & Power Deptt.)
In case of any shortfall a revised estimate
may also be submitted.
SOUTH DISTRICT
Construction of Sub-Jail Complex at
Namchi:
The P.C.E. cum Secretary showed his
displeasure on the absence of the
Jr.Engineer (Namchi).He was called up
telephonically and was directed to submit
the revised estimate for the construction of
the Sub-Jail Complex at Namchi by the 2nd
week of May failing which departmental
proceeding will be initiated against him.
The Superintending Engineer and the
Div.Engineer of the concerned division were
also instructed to ensure that the work is
completed on time. The need for full
cooperation amongst all the level of
officers for the complention of the task was
also highlighted.
Extension of the District Library at
Namchi:
The Superintending Engineer (S/W)has been
entrusted the task to purse the matter with
the Culture Affairs & Heritage Deptt about
the fund position for the extension of the
District Library at Namchi.
Construction of Alternate Ground at
Singithang
The work has been completed but the payment
has not yet been made. The Sr.Accounts
Officer has been instructed to ask for the
transfer of 100% resource from the Sports &
Youth Affair Deptt.
Construction of the Regional
Administrative Centre (R.A.C) at Karfectar:
The Superintending Engineer (S/W) has
directed to ensure the submission of the
revised estimate of the construction of the
R.A.C. by the 1st week of May which should
incorporate the central heating and cooling
system.
Construction of the Police Training
Centre Yangang (Phase II)
The 2nd week of May has been schedule for
the inauguration of the Police Training
Centre at Yangang. The water supply line has
to connected for which a No Objection
Certificate has been deemed essential from
the landowners.
NORTH/EAST DIVISION
Construction of Boundary Fencing at
Pakyong Sub-Division Officer Complex:-
The work has been physically completed but
the payment of the final bill has been held
up as the file is with the Vigilance Deptt.
Construction of S.D.M.Complex at Rongli:-
The Architect Cell was direct to expedite
the drawing of the gate for the
S.D.M.Complex.
There was a suggestion that a new outlook
could be given to the gate by adding a blend
of modernization and our state’s own
traditional architecture duly harmonizing
with the concept of the building.
The P.C.E.cum Secretary stressed on the need
of completing the project in all respect by
end of June 2008. |
|
| |
|
|
| |
Construction or Raj
Bhawan Complex:-
Decision to incorporate some changes as
highlighted by the field engineers could be
taken after inspecting the site by the PCE-cum
Secretary, Chief Engineer and other senior
officers in the next coming few days.
Construction of S.N.T. Office at Rangpo:-
The work of ground floor has been completed
as per the fund made available by the
Transport Department against the DPR
submitted for the entire building.
The Superintending Engineer (N/E) has been
asked to pursue the matter with the
Transport Department for further work.
Construction of Tribal School at Swayem:-
The PCE-cum Secretary and the Chief Engineer
expressed concern about the delay in
completing the work for which the field
official have been direct to give due
attention for early completion of work. So
that the complex can be made functional at
the earliest possible.
PROJECT DIVISION
Kolkata Guest House:-
The Div.Engineer (Project) has been directed
to submit the revised estimate for the
Kolkata Guest House at the earliest.
HEAD QUARTER DIVISION
Construction of Multipurpose Hall Cum
Gymnasium for S.A.P at Pangthang.
It was assured by the concerned field
official that the work will be completed by
mid- July. The Sr.Accounts Officer has been
instructed to correspond with the Police
Deptt for the release of resource.
STORE DIVISION
It was decide that the stock materials
in the store division should be properly
monitored. The materials brought in the
store division should be used for the same
work for which it had been procured.
For the proper function of the Store
division, the following persons have been
entrusted with the duties to look after the
works of the Store Division henceforth:-
(a) Miss Tenzing Pema, Jr.
Engineer,(planning) has been given the
additional charge of the Gangtok Store.
(b) Another Jr.Engineer proposed will be
posted at Jorethang shall hold the
additional charger of the Jorethang Store.
(c) The Jorethang Store shall be under the
charge of Superintending Engineer South/
West and the materials will be issued under
approval and signature of the Superintending
Engineer South/West in the indents.
(d) Smt.Snagay Diki Bhutia Assistant
Engineer (Planning) who has been transferred
to the development will shall be issued
under her approval and signature in the
indents.
(e) The Divisional Engineer (Planning) will
also hold the additional charge of both the
store at Gangtok and Jorethang.
(f) The Superintending Engineer (planning)
will continue to hold the additional charge
of the Store Division.
STATE GREEN MISSION
All the Assistant Engineers have been
directly to submit the status report of the
Green Mission Programme of 2007-08
undertaken by the Department as under:-
(i) Categories of plants planted;
(ii) Date of plantation;
(iii) Numbers survived;
(iv) The effect of the onslaught of
hailstorm and pre-monsoon rainfall on the
sapling planted, etc.
The report should reach the office of the
Superintending. Engineer (Planning) by
30.04.08 who will there after compile the
report and place it before to the Chief
Engineer by the 15th of May.
In order to achieve success of the vision of
the Government to make/convert Sikkim as a
green and eco-friendly state, the
Department’s higher authorities directed all
the field officials to provide green covers
by planting dubos other plants in all
government offices/ complexes by deploying
the department’s maintenance gangs.
Change in Design and Plan of the
Building/Change in Scope of Works. |
|
| |
The PCE- cum Secretary to
the Notice of all officers that there are
instance of their change in design and plan
of the buildings or change in scope pf works
carried out by the field engineers as
desired by the authorities of the line
department s during inspections without the
knowledge and approval of the higher
authorities of the department during
inspections without the knowledge and
approval of the higher authorities of the
department. As such, all field engineers
have been directed not to resolve to this
practice Henceforth, department/departments
desiring any deviation from the original
approved plan and design should be brought
to the notice of the higher authorities of
the department by the field engineers and
should thereafter only proceed ahead as per
the directions and instruction given by the
authority of the department. For this
purpose the authority/authorities desiring
any such change/changes should be requested
to obtain the prior approval of the
authorities of the Buildings & Housing
Department in the first instance.
Capacity Building Pogramme
It was highlighted that the west Division
achieved better result under the Capacity
Building Programme undertaking during
2007-08.
Some of the pertinent problems faced by the
various divisions in conducting the
programme in 2007-08 were highlighted as
under:-
(i) The inaccessibility of the trainees to
reach the training centres for
e.g. many identified trainees from the far
flung places in the various
constituencies could not reach the
identified training centres.
(ii) It was also observed that many of the
trainees were skilled workers
Already and hence the objective of making
unskilled workers as skilled workers was
defeated to certain extent.
Therefore, in order to maintain transparency
in future programmes, decision was taken to
screen the prospective trainees with the
help of Area Panchayats before enrolling
them as trainees.
In order to make the programme a result
orientated one, decisions were taken for the
ensuing programme of 2008-09:-
(i) The training programme should be
self-sustaining.
(ii) The number of trainees should be
reduced.
(iii) There should be centralized training
centre.
(iv) The duration of the training should be
increased.
(v) The areas where the training is to be
held should be specified.
(vi) The training should be
institutionalized.
(vii) In order to make the trainees
proficient in a particular field, the
training shall be imparted in a specific
field, as per the capability and aptitude of
the trainees.
(viii) For the above purpose, a screening
test of the trainees should be conducted by
the Asstt.Engineer assisted by the
Jr.Enginer. The concerned area Panchayat too
will be involved in the screening test.
(ix) The training Programme should be
residential one to achive the desired
result.
(x) The S.I.R.D. Karfectar has been
identified as one of the centres for the
ensuing training programme.
(xi) The previous trainees can also be
considered for further training for a period
of one month in order to enhance their
proficiency.
(xii) The previous trainees can also be
consider for further training for a period
of one month in order to enhanced their
proficiency.
(xiii) It was decide to cover as far as
possible all the Assembly Constituencies
except Sangha seat. For this purpose the
Nodal Officers of the department have been
directly to draw the training programees for
the current year duly identifying the
training centres and work out the trainee’s
strength as per the capacity of the training
centres vis-à-vis fund allocated for the
programme.
(xiv) Trip/kits purchased under the Capacity
Building Programme issued to the trainees
after the training.
(xv) It was proposed that the duration of
training for carpentry shall be fixed for a
period of two months and for painting and
masonry for one month.
(xvi) The following officers were entrusted
with the responsibility of the training
programme for the year 2008-09:-
(a) The Superintending Engineer (Planning)
and the Div. Engineer (Planning) as
the Nodal Officer and Assistant Nodal
Officer respectively.
(b) They will be assisted by the Div.
Engineer (Project) and Senior Architect.
(c) The Superintending Engineers of the
respective circle will coordinate with the
Nodal Officer for the programmes under their
respective jurisdictions.
(xvii) The Nodal Officer was instructed to
communicate with the S.I.R.D. for fixing up
the training schedule.
(xviii) It was also proposed to evaluate the
performance of the trainees at the end of
the training programme.
(xix) The Panchayats of the concerned
village shall be entrusted with the
responsibility of distributing the
certificate to the participants/trainees of
207-08.
INSTALLATION OF WEBSITE
The Superintending Engineer (Planning) has
been directed to ensure the installation of
the department website by May positively.
PAYMENT OF SALARY
The Muster Roll wages should be made in the
1st week of every month positively.
PERMISSION TO LEAVE THE STATION
All the officer has been advised not to
leave the district/ station without the
prior permission of the P.C.E- cum
Secretary. The Addl.Secretary has been
instructed to issue a circular in this
regard
2. PROGRESS REPORT OF ONGOING WORKS:-
Progress Report
The concerned Div. Engineers were instructed
to submit the Progress Report directly to
the Superintending Engineer (Planning) with
copy to the respective Superintending
Engineer of the circle.
Melli Composite Check Post
The PCE- cum –Secretary directly the
concerned Superintending Engineer to submit
the revised estimate for Melli Composite
Check Post latest by 5th May.
High Court (Phase-III)
The field engineers were directly to
expedite the progress of the work and were
also directed to avail the services of Shri.
Ashok Chettri, Jr. Engineer under Project
Sub- Division for necessary checking and
designing of reinforcement, if required.
CULTURAL CENTRE AT GANGTOK
The PCE- cum-Secretary observed that the
physical progress is not commensurate to the
fund released by the Culture Affairs and
Heritage Department. The field officials
were directed to expedite the progress.
CONSTRUCTION OF HERITAGE CENTRE AT
KHECHEOPARI
The Div. Engineer has been instructed to
purse the matter with the Gumpa Committee
for the early commencement of the work.
DISTRICT ADMINISTRATIVE CENTRE AT MANGAN
The Assistant Engineer (Mangan) has been
directed to verify the status of the land
pertaining to the District Administrative
Centre (DAC) at Mangan with the Dictrict
Collector (North) |
|
| |
|
|
| |
|
|
| |
|
|
| |
|
|
|