Tenth Five Year Plan |
|
| |
|
|
| |
REPORT ON THE SCHEMES
TAKEN UP BY BUILDINGS AND HOUSING DEPARTMENT
IN THE 10TH.FIVE YEAR PLAN HIGHLIGHTING
TARGETS AND ACHIEVEMENTS.
The buildings and housing department is
entrusted with the development of
infrastructure in the state. In this regard,
the department takes up construction of
government buildings only. The activities of
the buildings and housing department can be
broadly classified under the following two
budget heads:
A. Construction of Residential buildings
under the `housing sector`.
B. Construction of Non-residential buildings
under the ` Public works sector`
Construction of all government offices,
conference-banquet halls, stores come under
`public works sector` and construction of
all government quarters fall under `housing
sector.
Its expertise and experience is also
extended to the other departments for the
construction of buildings under their
department.
The building and housing department is
relentlessly continuing its developmental
activities by taking up construction of
residential buildings and non-residential
buildings in the state. Essentially the
department under the `Housing sector` takes
up construction of various categories of
quarters, classified as Class-I, Class-II,
Class- III and Class-IV quarters for
providing housing facilities to the
government officers and staff, and with
increasing number of government employees,
the demand for quarters have increased
manifold and to cope up with the situation,
the department has planned and constructed
number of residential quarters in the past..
Under `Public works` sector construction of
various office buildings, conference hall,
stores have also been completed
successfully. |
|
| |
|
|
| |
HOUSING - SECTOR - "
4216"
The activities covered under this sector
includes development of residential
accommodation both at the state quarters as
well as the districts and sub-divisional
levels for government employees.
Housing being a state subject is an integral
part of our policy of improvement of human
settlements and economic developments. The
main idea behind construction of residential
quarters is not only to improve housing
conditions and for providing basic amenities
to the government employees but also
emphasizes new construction and up-gradation
of housing besides generating revenue
through house rent and license fee deducted
from their salaries.
Keeping in view of above, an outlay of Rs.
2500.00 lakhs has been approved in the tenth
plan outlay under ‘Housing sector’ which
includes the spillover liabilities required
for the on-going schemes taken up during the
previous 9th. Plan period.
4216-Capital outlay on Housing.
01-Government residential buildings
01.106- General Pool Accomodation
60- Construction (PWD) |
|
| |
|
|
| |
60.00.71 – STAFF
QUARTERS AT GANGTOK..
10th. Plan Outlay. ----- ----- ------ Rs.
1000.00 lakhs.
Annual Plan 2002-03 (Actual Expenditure) ---
Rs. 146.47 lakhs.
Annual Plan 2003-04 (Actual Expenditure) ---
Rs. 129.26 lakhs.
Annual Plan 2004-05 (Actual Expenditure) ---
Rs. 215.00 lakhs.
Annual Plan 2005-06 (Annual Expenditure) ---
Rs. 285.62 lakhs.
Annual Plan 2006-07 (Outlay) --- Rs. 146.00
lakhs.
The proposal is to continue the spillover
liabilities of the 9th. Plan and complete
them during the 10th. Plan period. Number of
new proposals has also been suggested for
taking them up during the 10th. Plan period.
The major schemes /projects are construction
of approach road,drainages etc. at Sichey
Housing Colony, reconstruction of old and
dilapidated single storied residential
structure scattered around Gangtok.
Construction of Sichey Housing Complex
having 12-unit Class- I quarter, 30 unit
Class- II quarter, 120 units Class-III
quarter, 162 units of Class-IV quarter with
club-cum- library and a shopping complex
have also been proposed by the department.
As of now various works like construction of
6-unit Class- I quarter at Namnang and
Sichey, 6 and 12 units Class –III quarter at
Sichey, 3 nos. of ADC’s quarter, 3 nos. Clss-II
and 50 nos. of Class-IV quarters at Raj-
Bhavan complex have been completed. |
|
| |
|
|
| |
60.00.72 – QUARTERS AT
OTHER DISTRICTS
10th. Plan Outlay. ----- ----- ------ Rs.
400.00 lakhs.
Annual Plan 2002-03 (Actual Expenditure) ---
Rs. 19.22 lakhs.
Annual Plan 2003-04 (Actual Expenditure) ---
Rs. 50.00 lakhs.
Annual Plan 2004-05 (Actual Expenditure) ---
Rs. 24.97 lakhs.
Annual Plan 2005-06 (Annual Expenditure) ---
Rs. 29.50 lakhs.
Annual Plan 2006-07 (Outlay) --- Rs. 9.00
lakhs.
The district head-quarters namely Mangan,
Namchi,Gyalshing are facing acute shortage
of residential accommodation for the
government employees. Although it is very
difficult to fulfill the entire requirement
during the 10th.plan period, the department
has proposed to take up construction of
construction of Class- I and Class-II
quarters at Mangan and Gyalshing including
District collectors quarter at Gangtok. |
|
| |
|
|
| |
60.00.73 – QUARTERS AT
SUB-DIVISION LEVEL.
10th. Plan Outlay. ----- ----- ------ Rs.
200.00 lakhs.
Annual Plan 2002-03 (Actual Expenditure) ---
Rs. 54.20 lakhs.
Annual Plan 2003-04 (Actual Expenditure) ---
Rs. 39.76 lakhs.
Annual Plan 2004-05 (Actual Expenditure) ---
Rs. 59.97 lakhs.
Annual Plan 2005-06 (Annual Expenditure) ---
Rs. 113.94.lakhs.
Annual Plan 2006-07 (Outlay) --- Rs. 50.00
lakhs.
It is proposed to construct atleast Class-
III and Class-IV quarters at different
sub-divisions like Ravangla,Soreng and
Pakyong. |
|
| |
|
|
| |
60.00.74 – QUARTERS AT
OTHER PLACES.
10th. Plan Outlay. ----- ----- ------ Rs.
150.00 lakhs.
Annual Plan 2002-03 (Actual Expenditure) ---
Rs. 9.78 lakhs.
Annual Plan 2003-04 (Actual Expenditure) ---
Rs. 9.88 lakhs.
Annual Plan 2004-05 (Actual Expenditure) ---
NIL.
Annual Plan 2005-06 (Annual Expenditure) ---
Rs. 3.00 lakhs.
Annual Plan 2006-07 (Outlay) --- Rs. 5.00
lakhs.
Similarly there is acute shortage of
residential accommodations for the
government employees at places other than
the sub-divisions head quarters. Thus it has
been proposed to construct staff quarters at
these places to ease out the problem to a
great extent. |
|
| |
|
|
| |
60.00.75 – QUARTERS
FOR MINISTERS.
10th. Plan Outlay. ----- ----- ------ Rs.
400.00 lakhs.
Annual Plan 2002-03 (Actual Expenditure) ---
Rs. 113.92 lakhs.
Annual Plan 2003-04 (Actual Expenditure) ---
Rs. 149.96 lakhs.
Annual Plan 2004-05 (Actual Expenditure) ---
Rs. 94.97 lakhs.
Annual Plan 2005-06 (Annual Expenditure) ---
Rs. 107.01 lakhs.
Annual Plan 2006-07 (Outlay) --- Rs. 120.00
lakhs.
In view of the shortage of quarters for
VIPs’,additional numbers of quarters has
been suggested and the works taken up during
the 9th. Plan would be carried out in the
10th. Plan period for completion.Further
addition, alteration and extension to the
existing VIP bunglows has also been
proposed. |
|
| |
|
|
| |
60.00.76 –
ADDITION,ALTERATION & RENOVATION OF
QUARTERS.
10th. Plan Outlay. ----- ----- ------ Rs.
350.00 lakhs.
Annual Plan 2002-03 (Actual Expenditure) ---
Rs. 19.95 lakhs.
Annual Plan 2003-04 (Actual Expenditure) ---
Rs. 68.55 lakhs.
Annual Plan 2004-05 (Actual Expenditure) ---
Rs. 53.45 lakhs.
Annual Plan 2005-06 (Annual Expenditure) ---
Rs. 51.57 lakhs.
Annual Plan 2006-07 (Outlay) --- Rs. 60.00
lakhs.
A major problem in renovating and altering
the existing residential buildings in the
state has emerged during the 9th.plan
period. A great number of quarters are in a
dilapidated condition and needs immediate
alteration and renovation. A certain amount
of fund if provided in the 10th. Plan could
be utilized for the alteration and
renovation of the quarters.This would not
only help in adding value to these assets
but also ease out the shortage of
accommodation for the government employees
in the state. |
|
| |
|
|
| |
60.00.77 – QUARTERS FOR M.L.A.
10th. Plan Outlay. ----- ----- ------ Rs.
50.00 lakhs.
Annual Plan 2004-05 (Actual Expenditure) ---
Rs. 49.28 lakhs.
Annual Plan 2006-07 (Outlay) --- Rs. 110.00
lakhs. |
|
| |
|
|
| |
PUBLIC-WORKS. “4059”
A great emphasis was given in the 9th.plan
period to bring administration closer to the
people by way of de-centralization of the
administrative structure in the state. For
the purpose the basic infrastructure was
required in the form of the non-residential
buildings viz. the office buildings in and
around the capital town of Gangtok and in
the districts and sub-divisions. High
priority is also given in the
infrastructural development at Raj-Bhavan.
Many of the departments that were earlier
housed in a private rented buildings have
been provided with the government office
accommodation in the building constructed
during this period., to name some of the
office buildings there is the Tashiling
Annexe – I building near Power department
and Tashiling Annexe –II building near
Government press building at Gangtok.
However, the shortage of office
accommodation still remains with the
developmental activities taking place in the
fast pace. Hence, there is a graet demand
for construction of office buildings not
only in Gangtok but also in district head
quarters and sub-division levels.
Keeping in view the emphasis required in the
10th. Plan period, projects have been
prepaqred and spillover required for
on-going projects have been taken care of in
the 10th. Plan proposals, an outlay of Rs.
3000.00 lakhs has been approved in the 10th.
Plan period. The outlay of Rs. 3000.00 lakhs
has been found to be inadequate considering
the spillover liabilities of works that were
undertaken during the 9th. Plan period and
paid/completed during the 10th. Plan period.
The workwise details are summarized below:
2059 – Public-Works.
80 – General.
001 – Direction and Administration
40 – Chief Engineer(Buildings) Estab.
004 – Planning and Research.
TENTH PLAN OUTLAY ------ -------- ------ Rs.
450.00 lakhs.
Annual Plan 2002-03 (Actual Expenditure) ---
Rs. 73.02 lakhs.
Annual Plan 2003-04 (Actual Expenditure) ---
Rs. 84.90 lakhs.
Annual Plan 2004-05 (Actual Expenditure) ---
Rs. 100.69 lakhs.
Annual Plan 2005-06 (Annual Expenditure) ---
Rs. 157.13 lakhs.
Annual Plan 2006-07 (Outlay) --- Rs. 137.00
lakhs.
An outlay of Rs. 400.00 lakhs has been
proposed for meeting up the administrative
expenses of the department including
strengthening of the material testing
laboratory, planning and research activities
and training of the office personnel.
4059 – Capital Outlay and Public Works.
01 – Office Buildings
60 – Other Buildings
60.051 – Construction
03 – Buildings and Housing Department. |
|
| |
|
|
| |
03.00.71 –
SECRETARIAT AT GANGTOK.
TENTH PLAN OUTLAY ------ -------- ------ Rs.
25.00 lakhs.
Annual Plan 2002-03 (Actual Expenditure) ---
Rs. 2.26 lakhs.
Annual Plan 2003-04 (Actual Expenditure) ---
Rs. 0.67 lakhs.
Annual Plan 2004-05 (Actual Expenditure) ---
Rs. 4.55 lakhs.
Annual Plan 2005-06 (Annual Expenditure) ---
Rs. 1.35 lakhs.
Annual Plan 2006-07 (Outlay) --- Rs. 5.00
lakhs.
A sum of Rs. 25.00 lakhs has been proposed
forr renovation,alteration of the old
secretariat building for creation of
additional space for offices and toilets.
03.00.72 – OTHER OFFICE COMPLEX AT GANGTOK.
TENTH PLAN OUTLAY ------ -------- ------ Rs.
100.00 lakhs.
Annual Plan 2002-03 (Actual Expenditure) ---
Rs. 8.47 lakhs.
Annual Plan 2003-04 (Actual Expenditure) ---
Rs. 10.05 lakhs.
Annual Plan 2004-05 (Actual Expenditure) ---
Rs. 3.76 lakhs.
Annual Plan 2005-06 (Annual Expenditure) ---
Rs. 5.88 lakhs.
Annual Plan 2006-07 (Outlay) --- Rs. 5.00
lakhs.
During the 9th plan period Tashiling Annexe
–I and Tashiling Annexe –II, totaling
roughly 50,000 sq.ft. of office
accommodation has been completed. The
provision given in the 10th. Plan would
cater mainly for spillover liabilities and
addition,alteration of the office buildings.
03.00.73– OFFICE COMPLEX AT DISTRICT HEAD
QUARTERS.
TENTH PLAN OUTLAY ------ -------- ------ Rs.
500.00 lakhs.
Annual Plan 2002-03 (Actual Expenditure) ---
Rs. 49.41 lakhs.
Annual Plan 2003-04 (Actual Expenditure) ---
Rs. 95.82 lakhs.
Annual Plan 2004-05 (Actual Expenditure) ---
Rs. 84.84 lakhs.
Annual Plan 2005-06 (Annual Expenditure) ---
Rs. 49.00 lakhs.
Annual Plan 2006-07 (Outlay) --- Rs. 60.00
lakhs.
The administrative infrastructure have been
provided in almost all the district head
quarters in the state. Proposals to provide
extensions to the existing District
Administrative Centre (DAC) at Gyalshing and
at Mangan has been finalized. Extension of
DAC at Namchi has been completed.
03.00.74 – OFFICE COMPLEX AT SUB-DIVISION
LEVEL.
TENTH PLAN OUTLAY ------ -------- ------ Rs.
375.00 lakhs.
Annual Plan 2002-03 (Actual Expenditure) ---
Rs. 59.21 lakhs.
Annual Plan 2003-04 (Actual Expenditure) ---
Rs. 74.28 lakhs.
Annual Plan 2004-05 (Actual Expenditure) ---
Rs. 85.76 lakhs.
Annual Plan 2005-06 (Annual Expenditure) ---
Rs. 64.76 lakhs.
Annual Plan 2006-07 (Outlay) --- Rs. 72.00
lakhs.
The Administrative infrastructure at
Sub-division level viz. at
Chungthang,Pakyong,Soreng and at Ravangla
has been completed. The provision of Rs.
375.00 lakhs has been proposed to take up
establishment of Sub-division office
including the cost of the land at Rongli and
composite office buildings at Jorethang. The
construction of Sub-Division office complex
at Rongli and construction of Regional
Administrative Centre at Jorethang has
already started. Extension of S.D.M. Office
complex at Soreng has been proposed.
03.00.75 OFFICE COMPLEX FOR P.W.D.
TENTH PLAN OUTLAY ------ -------- ------ Rs.
50.00 lakhs.
Annual Plan 2002-03 (Actual Expenditure) ---
Rs. 2.50 lakhs.
Annual Plan 2003-04 (Actual Expenditure) ---
Rs. 4.12 lakhs.
Annual Plan 2004-05 (Actual Expenditure) ---
NIL.
Annual Plan 2005-06 (Annual Expenditure) ---
Rs. 4.95 lakhs.
Annual Plan 2006-07 (Outlay) --- Rs. 5.00
lakhs.
The Administrative block for the Engineering
Departments, viz. Roads and Bridges, P.H.E.,
Buildings and Housing and Irrigation and
Flood Control Departments have since been
completed. The amount of Rs. 50 .00 lakhs
has been proposed in the 10th. Plan to meet
up the expenditure for the construction of
Car parking/Store and Annexe building of
Nirman Bhavan to meet the requirement of
additional office space.
03.00.76 OFFICE COMPLEX FOR JUDICIARY
ADMINISTRATION (STATE SHARE).
TENTH PLAN OUTLAY ------ -------- ------ Rs.
150.00 lakhs.
Annual Plan 2002-03 (Actual Expenditure) ---
Rs. 5.27 lakhs.
Annual Plan 2003-04 (Actual Expenditure) ---
Rs. 9.94 lakhs.
Annual Plan 2004-05 (Actual Expenditure) ---
Rs. 57.97 lakhs..
Annual Plan 2005-06 (Annual Expenditure) ---
Rs. 180.00 lakhs.
Annual Plan 2006-07 (Outlay) --- Rs. 85.00
lakhs
Up-Gradation of Judicial Administration for
Sikkim has been completed in the 9th. Plan.
During the 9th. Plan period the civil courts
in the districts has been completed. The
provision of Rs. 150.00 lakhs has been
proposed for construction of quarters for
high court judges including cost of land at
Gangtok,and construction of quarters for
judiciary at Namchi and at Gangtok including
cost of land. Construction of Judiciary
complex having quarters for Honourable Chief
Justice, Honourable Judges etc. has been
taken up.
This is a scheme on 50:50 sharing basis
between the centre and the state government.
The state government has not been able to
provide matching grant due to which central
grant has been stalled temporarily since
2003-04.
03.00.78 OTHER BUILDINGS.
TENTH PLAN OUTLAY ------ -------- ------ Rs.
1300.00 lakhs.
Annual Plan 2002-03 (Actual Expenditure) ---
Rs. 670.38 lakhs.
Annual Plan 2003-04 (Actual Expenditure) ---
Rs. 310.27 lakhs.
Annual Plan 2004-05 (Actual Expenditure) ---
Rs. 502.91 lakhs..
Annual Plan 2005-06 (Annual Expenditure) ---
Rs. 347.94 lakhs.
Annual Plan 2006-07 (Outlay) --- Rs. 130.00
lakhs
During the 9th. Plan period, a
Conference-cum- Banquet Hall and Guest House
at Gangtok were commenced and completed in
the year 2003. Similarly construction of
Guest House at Pakyong was started during
9th.plan period and was completed in the
10th. Plan period.
The details of some of the important
buildings already taken up and to be taken
up is highlighted below:
Conference-cum- Banquet Hall (CHINTAN BHAVAN).
The work has been completed physically but
payment is pending due to fund constraint.
Guest House (CIRCUIT HOUSE) at Gangtok.
The work has been completed physically but
due to fund constraint the payment is yet to
be made during the current financial year.
Guest House at Kolkata..
The work is under progress. The land for the
project is leased out by the West Bengal
government which is located at salt lake in
Kolkata. This is being constructed for
providing accommodation to V.I.Ps’ and
officers visiting Kolkata on official tour.
Guest House at Siliguri:
The guest house at Siliguri is presently
being constructed in the land belonging to
the Sikkim government. The guest house would
provide for accommodation to the
V.I.P.s’,and officers visiting Siliguri for
official work.
Renovation of Assembly Building:
Roof treatment is proposed to be taken up
for the Assembly House building along with
some addition and alteration.
High Court - Annexe Building
The construction of High Court Annexe
building has been completed during 2003-04.
However the payment is to be made during the
current financial year due to fund
constraint.
Construction of Raj-Bhavan at Gangtok.
The existing Raj-Bhavan is an ancient
structure and the condition of the structure
is far from safe. In fact the present
structure has out lived it’s life span and
needs immediate attention either for major
renovation or for new construction. Further
number of cracks have developed due to
moderate earthquake very recently.
Retrofitting measures have to be taken up
for strenghthening of the structure for
which estimates have been prepared by the
department.
Guest House at Karfectar:
The guest house at Karfectar in South Sikkim
has already been completed.
Alteration and Renovation of the Archives
Building at Gangtok.
The archive building is housed in the old
assembly house building, which is infact a
very ancient structure. It is proposed to
renovate the old building with major
alteration works and face lifting.
03.00.77 – ADDITION, ALTERATION AND
RENOVATION OF OFFICE BUILDINGS.
TENTH PLAN OUTLAY ------ -------- ------ Rs.
50.00 lakhs.
Annual Plan 2002-03 (Actual Expenditure) ---
Rs. 6.37 lakhs.
Annual Plan 2003-04 (Actual Expenditure) ---
Rs. 9.43 lakhs.
Annual Plan 2004-05 (Actual Expenditure) ---
Rs. 13.34 lakhs.
Annual Plan 2005-06 (Annual Expenditure) ---
Rs. 18.26 lakhs.
Annual Plan 2006-07 (Outlay) --- Rs. 71.00
lakhs.
The need for addition,alteration and
renovation of very old government buildings
in the state has been felt very badly.
Specific provision for renovation,
alteration not provided in the earlier plan
periods have left many of the important
government buildings in a very pathetic
state. Therefore in order to add value to
the existing govenment assets, major
renovation to the some of the prominent
public buildings is a must.
60.051 – Construction – 03-45-03-45-71
Construction of Raj-Bhavan Annexe.
TENTH PLAN OUTLAY ------ -------- ------
NIL.
Annual Plan 2002-03 (Actual Expenditure) ---
NIL.
Annual Plan 2003-04 (Actual Expenditure) ---
Rs. 99.85 lakhs.
Annual Plan 2004-05 (Actual Expenditure) ---
Rs. 199.96 lakhs.
Annual Plan 2005-06 (Annual Expenditure) ---
Rs. 471.24 lakhs.
Annual Plan 2006-07 (Outlay) --- Rs. 300.00
lakhs.
Extension of yard including construction of
Banquet hall (now called ‘Ashirwad Bhavan’)
at Raj-Bhavan has been completed in 2005-06.
Construction of Type – IV quarters at Raj-
Bhavan has also been completed just
recently.
Major construction works
commenced/undertaken during 10th five year
plan but would spill over to 11th. five year
plan with details are as under:
Budget Head: 4059 – Public works:
1. Circuit House at Gangtok.
2. High Court Phase – I at Gangtok.
3. High Court Phase – I at Gangtok.
4. DCN Conferencing System at State Level
Conference Hall at Gangtok.
5. Chintan Bhavan at Gangtok.
6. Security Check post at Rangpo.
7. Guest House at Kolkata.
8. Regional Administrative Centre at
Jorethang.
9. Sherpa Community Centre at Okherey.
10. View Tower at Pelling.
11. Multi-Purpose Hall-cum- Gymnasium for
Sikkim Armed Police at Pangthang.
12. District Administrative Centre at Namchi.
13. Sub-Divisional Magistrate office at
Soreng.
14. (a) SDM Complex at Rongli.
(b) Approach road to SDM Complex at Rongli.
15. (a) Infrastructure development work for
Raj-Bhavan complex at Gangtok.
(b) Class – III (16 unit) quarter in - 4
block at Raj-Bhavan complex.
(c) Barrack,Sentry posts, Frisking
Centre,General room and other allied works
at
Raj-Bhavan complex , Gangtok.
16. (a) Judiciary Complex at Sichey,
Gangtok.
(b) High Court Phase –II, Gangtok.
(c) Major renovation and providing furniture
furnishing to VIP qtrs.of Hon’ble Chief
Justice at Forest Colony, Gangtok.
The progress of the works as mentioned under
sl no. 1 to 6 above has been completed 100%
but its’ financial progress is yet to be
achieved due to fund constraints. Other
works as indicated under Sl. No. 8 to 16 are
still under progress and is likely to spill
over to the next financial year.
Detail showing Physical and Financial
progress of the works taken up in the 10th
five year plan including list of spillover
schemes is enclosed with the report at
Annexure – I and II and III
SD/-
Superintending Engineer (Planning),
Buildings and Housing Department. |
|
| |
|
|
| |
|
|
|